Candy Window as a Story Project: Update

candy window drawing

I really thought that my window location was set but I was wrong. It has moved twice since the last post. Now I hope that it really is decided! But I’m moving forward anyway. I finished Step Two: Organize, today by searching through my candy stash to see what I already have that will work. I’m in good shape except for the larger candy areas like the sky, the doghouse etc.

So now to work on Step Three: Analyze.

Part 1: Assess – I think my plans for this years window are as reasonable as I can make them. We are hoping to do some fun things with computer controlled lights but the design is such that if that doesn’t happen it will be OK. I’ve been careful not to let the size of the window get too large. With getting a late start on things and a new puppy coming time is limited and larger objects means more candy and more candy takes more time to glue it on. This will be one of my smaller windows at about 3 feet wide and 5 feet tall and 2.5 to 3 feet deep. Hopefully it won’t feel small when it is done. So the project moves forward.

Part 2: Plan – I’ve looked at all the parts and pieces of the window and come up with more than 50 tasks that need to be done. Some are fairly simple and easily completed while others might need to broken down into even smaller task when I get involved in the reality of doing that part of the project. I’ve done enough candy windows that there shouldn’t be too many surprises.

Part 3: Timeline – I have a firm deadline (the unveiling on 7th) so the thing the timeline does for me is to help me make sure that I get enough stuff done early so that I don’t have to pull all-nighters to make my deadline. I have it when I have to do that. Creating the window looses all it joy when there is too much pressure. So here is my rough timeline:

  • window box size – August
  • list of construction materials – August
  • purchase construction materials – August
  • choose candy – August
  • build structure – September
  • purchase candy – September
  • purchase other supplies – September
  • paint structure – September
  • attach candy – September through November
  • final detail & fix problems – November
  • promotional stuff – November & December
  • install window – before December 7th
  • unveiling – December 7th

The timeline is still pretty rough and so I’ll be making detailed plans and goals each week. My first deadline is to get all the structure built (if possible) by the time Pup “E” comes on September 6th. Timelines need to be adaptable to changing circumstances yet help the project stay on track to meet long-term goals.

Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s